Build lease transfer BLT
Contents |
[edit] Introduction
Procurement is the process of purchasing goods or services. There are many different routes by which the design, construction and operation of a built asset can be procured.
Build, lease, transfer (BLT) is a form of procurement in which a private contractor builds (and finances) a project on behalf of a public sector partner (or client) and then leases the project back to the client for a predetermined period (referred to as the lease or concession period).
The development is then occupied by the client, who pays rent to the contractor for a minimum term under a leasehold agreement. The level of the rent is generally a function of the total development costs (including land acquisition, design, construction and operating costs).
At the end of this period, the contractor transfers the ownership of the project to the client for a price that was previously agreed.
This is a type of public private partnership (PPP). PPPs are a very broad range of partnerships in which the public and private sectors collaborate for some mutual benefit. PPPs can be arranged with either central or local government.
In theory, one of the benefits of this sort of procurement route is that the contractor has to consider the full life cycle of the development when making design and construction decisions. The drawbacks include the complexity of project agreements, and the difficulty of estimating costs and risks over long periods. Private Finance Initiative (PFI) projects, a form of PPP, have come under significant criticism for not delivering value for money to public sector clients.
[edit] Operations responsibilities
In some instances, the public sector partner may include operations in its BLT arrangement. However, it is more common for the client to handle operations while the contractor takes responsibility for maintenance during the period of the lease. At the conclusion of the concessionary period, maintenance (and operations, if applicable) typically reverts to the client.
This procurement method is sometimes used for healthcare, education and transportation facilities, although it may be suitable for other types of public projects such as roads, bridges, dams, railways, tunnels, and so on, or facilities such as prisons, libraries, leisure centres and so on.
[edit] Similar models
Related forms of procurement (some of which are essentially different descriptions of the same process) include:
- Build, lease, operate, transfer (BLOT) model, in which a private contractor builds a project on leased public land and operates the facility for the duration of the lease; once the lease is completed, ownership is transferred to the public entity or client.
- Build, operate, transfer (BOT), whereby the private organisation does not own the project as an asset, they merely receive a concession to operate it for a period of time. See Build operate transfer BOT.
- Build, own, operate, transfer (BOOT), in which the private organisation undertakes a public project and is then granted the right to own, maintain and operate the project for a set period of time, during which they can draw fees from users of the asset. Once the time period has elapsed, the control of the project transfers to the public sector partner, either freely or for a fee that is stipulated in the original contract.
- Design, build, finance and operate (DBFO), which also assigns the design responsibility to the private organisation.
- Design, build, finance, transfer (DBFT), which is a project delivery method that allows a contractor with expertise in design, construction and financing to be appointed to design, construct and arrange financial resources for the works. This is similar to design build finance and operate (DBFO), other than the contractor eventually transfers ownership of the project back to the client.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.